You can read a month-by-month history of the project so far. Just click on the year or month to reveal the report.


By the middle of December, the demolition of the former MFI Showroom was finally completed. The site was completely cleared making way for the excavation of the foundations to begin. Progress has been good due to the very mild weather this year and no major issues were encountered during the demolition.
Excavation of the foundations also began this month and an interesting feature was found quite early on. A cave was uncovered just below ground on the North side of the site. It extended about 3m into the cliff face and about 4m out under the proposed new foundations for the building (just below the creche to be precise!). This was a slight setback, although a solution was proposed and work was able to continue. By the end of the month, the piling for the foundations was complete along with most of the excavation work.
Aside from the visible work taking place on-site, discussions were continuing regarding the Audio-Visual installation, Kitchen fit-out and the all important matter of the interior design and furniture selections!

November 2011 will forever be remembered as the month that building work actually started on the new Cornerstone Church Centre on the Castle Boulevard site. On Tuesday 8th November, members of the church staff team, elders and representatives from GF Tomlinson gathered for a short ground-breaking ceremony on the site to officially mark the beginning of the construction phase of the project.
At the ceremony, Peter reminded us, 'we are building for a hundred years of gospel ministry because Jesus Christ is the same yesterday, today and for ever.' BBC Radio Nottingham were also present to record the occasion (the interview can be found on the media page of the building website.
Work quickly got underway with the establishment of the site cabins, fencing and hoardings. Demolition started soon after and by the end of the month there was just a small remnant of the shell of the west building left on the site.

On Monday 10th October, we issued a letter of intent to GF Tomlinson Building Ltd. for the contract to build the new Cornerstone Church Centre on Castle Boulevard. This marked the end of a selection process that began in January with a long list of nearly 20 potential contractors. Issuing the letter of intent signified our commitment to the contract and enabled the building contractor to dedicate additional resource to the project and start preliminary background work in lieu of a fully agreed contract.
Established in 1892, GF Tomlinson are one of the region's largest building contractors with offices across the East and West Midlands. They have a portfolio of successful projects in the region spanning a broad range of different sectors.
A significant amount of work was carried out to identify ways to use energy from renewable sources and this was been a key area of focus throughout the tender process. This was a tricky problem to solve as we have targets that we need to meet as well as budget considerations to try and balance.
Having evaluated a number of different options, we agreed to install Solar Photovoltaic panels on the roof of the new building. This will hopefully enable us to offset a significant proportion of our electricity usage and may also be source of revenue through the Government’s ‘Feed-In-Tariff’ scheme for energy micro generation.

Over the summer break the shortlisted building contractors worked on producing their responses to our invitation to tender. The responses were all received towards the end of August for us to review.
Unfortunately, the quotes we received were higher than our business plan expectations and, in some cases, significantly so. This was naturally a big setback and not the best news to be greeted with on returning from summer holidays! Despite this initial setback, discussions and negotiations took place with the leading building contract to identify ways to make savings to bring the price down to acceptable levels. The discussions were positive and very good progress was made towards agreement on a contract sum.

After months of detailed design, planning and estimating, we finally issued the tender package to a short-list of six building contractors. Bids were expected to be received towards the middle of August, when the decision making process would begin.
There was a huge amount of documentation produced, covering architectural design, engineering designs (structural, mechanical, electrical and acoustic), the proposed legal contract and all of the pre-construction investigation reports that were commissioned. Many of these documents are available on the Design page.

The Gift Day held this month was yet another encouragement along the way, raising an additional £110,000 towards the project. This kept the project on track with the business plan and enabled us to continue forward with the tender process.
On Thursday 23rd June, the church members voted overwhelmingly in favour of a special resolution to develop the Castle Boulevard site, approving the design and associated finance plans. This means that we were able to issue tender documents with a view to appointing a main building contractor.
Work continued on the detailed design aspects of the project, working towards the production of the Employers Requirements Document. Detailed finishes schedules (doors, ceilings, floors, ceilings, windows, etc.) have been produced and the final touches added to the overall design.

On Wednesday 25th May the Nottingham City Council Development Control Committee unanimously approved our application for the new church building on Castle Boulevard. This decision marks another significant milestone along the way to establishing a centre for Biblical teaching, Gospel-centred ministry and mission for generations to come. The decision also clears the way for us to proceed with the selection of a main building contractor, subject to the church’s approval of the design and financial plans.

This month, modified designs were produced which we hope will address the concerns raised at March's Development and Control Committee meeting. The main changes are to the auditorium comprising a reduced cladded roof area, different cladding material in a darker colour and the addition of a series of vertical windows to the south wall of the auditorium. The proposed designs were scheduled to be presented for approval at May's committee meeting.
Plans for another week of prayer and a gift day in June were announced. The week of prayer will begin on the 12th June and the gift day will be on Sunday 19th June.

On 23rd March, the City Council Development and Control Committee met to review our planning application. A decision on the application was deferred due to concerns expressed by council members over the design. We are currently looking at how we can revise the designs to address comments from the committee, with a view to re-presenting the design for approval at a future meeting.
Please continue to pray for these ongoing design discussions and for wisdom to know how to proceed with the project over the coming weeks. You can check on progress and any updated images in the design section of the website.
In March, significant work was done to produce a business and finance plan for the building project. This was in readiness for significant decisions to be made by the church regarding the move to the next stage of the project. Work also began on the procurement process, with about 15 building contractors requested to provide initial company background information. This list was reduced to a shortlist of 6 companies who will be invited to tender for the contract once the church has voted to proceed.

Throughout February, further work was done on the design and layout of the interior of the building. Fnal draft designs for the floor layouts, right down to details on the location of sinks, cupboards, power points and lighting were produced. Each room was designed with a primary purpose in mind, but also with a view to being as flexible as possible in their potential usage. Decisions were also made on external materials for the building and the overall landscaping of the site.
The latest floor plans can be seen on the design pages of the building website.

At the end of December, we submitted our application for planning permission to create a new church building on Castle Boulevard. This represented another significant milestone for the project and marked the transition into the detailed design and procurement phases of the project. The application was validated early in January and a decision notice expected in early April.
Having already obtained permission to change the use of the site to a place of religious worship in 2009, this application was to secure specific planning permission to build the proposed scheme on the site. The application focussed primarily on the external aspects of the building and consisted of over 70 individual documents and drawings produced by a team of professional disciplines including architects, engineers (acoustic, mechanical, electrical, structural and civil) and specialist consultants (planning, highways, environmental and ecological).
While the application was being reviewed through the consultation process, the design team starts work on the internal and more detailed technical aspects of the design. This is expected to take three months, to enable us to be ready to go out to tender for the building contract. There is still a huge amount of work to do and we are potentially only just beginning the really tricky part of the project!


Having worked on a range of different options, new designs were issued this month. The designs were produced to a constraint of about 2,500m2 in an attempt to keep the budget to a manageable level as well as attempting to address initial concerns raised by planning officers in May. This latest design differs from previous versions in a number of ways:
The scheme includes a 750-seat auditorium (without a balcony), a creche, a range of different sized meeting rooms, a kitchen, offices and a large welcome and meeting area. More detail on the internal layout of the rooms, etc. can be found on the design pages of the website.
Throughout November, over 50 volunteers from across Nottingham braved the snow, ice and cold conditions (inside and out!) to check, pack and sort over 11,000 shoe boxes to be sent to children of all ages in Africa and Eastern Europe. It was great to have a bustle of activity on the site and it was tremendous to see a large container lorry depart with so many gifts at the end of the month.

At the Elders' day in September, the Elders discussed and prayed for the future of the project and the ministries of the church. Having reviewed the finances of the project and the latest design options, it was decided to constrain the design brief to a floor space total of 2,500m2, with a view to meeting a target budget of approximately £3million. More detail can be found in the October newsletters
Well done to those hardy souls who came along to the special Prayer and Praise meeting in the West Building! It was certainly a different experience to worshipping in the school hall and gave us another chance to become more acquainted with the site of our future home. This was something of a ‘one-off’ experiment, as there are some things we need to sort out if we are to hold these kind of meetings more often. We will review what needs to be done in order for us to use the West Building for other meetings in the future. Watch this space!
This month, we installed three new signs on the Castle Boulevard site. Just another small step along the road of establishing our presence at our new home!

A great deal of work has been put into looking at alternative design options following comments from the City Council Planning Officers. A number of revisions have been proposed and revised cost estimates are being worked on to establish the best option to take forward. These discussions are proving a tricky balance between the need to keep the budget under control with the desire to have a more attractive building that will enhance the local area.
On Saturday 24th July, the Cornerstone Church Office moved to Castle Boulevard. The Office has been located at the school for 5 years, having moved from Beeston town centre in the summer of 2005. With the school now needing to use the classroom space, we need to vacate the offices at the end of this academic year. The decision was made to move the offices to Castle Boulevard to give us a presence on the new site.
We were blessed with a pretty hot day when the time finally came for us to move. An army of brave lifters and movers took on the task of loading and unloading two lorry loads of books, furniture, books, accounts, computers and books. Everything was safely transferred and the office was finally up and running the following Tuesday ...

This month, we received feedback from the Planning Office on our proposed designs. Unfortunately the feedback was not positive and a number of specific improvements were requested before a formal planning application is submitted. The key concerns were that the building still bore too great a resemblance to a retail warehouse, there was insufficient street-level activity along Castle Boulevard and there needs to be greater separation between the different elements of the building (auditorium and meeting rooms).

Sadly, some time between the 25th and 26th May, the buildings on Castle Boulevard were broken into and copper piping and electrical cable stolen. Whilst the East Building was left in a terrible mess, the West Building suffered greater damanage as the removal of pipes caused the entire building to flood. Thanks to a number of willing volunteers, the damage was cleared up in a couple of days and the building of the new offices was not significantly affected.

The Cornerstone Church Office is set to move to the Castle Boulevard site in the summer after the School requested use of the classrooms that have been the home of the Church Office for several years. This will give us the opportunity to be present on the new site throughout the week and should help with security as well as getting used to the new neighbourhood. Plans are being drawn up to create a small area of offices in the West Building (the former warehouse).
Design work has continued since the beginning of the year and a proposed design was presented to the church members at the Annual General Meeting, where the decision was taken to pursue this option further into the planning stage. The proposed scheme has a gross internal area of approximately 3000m2 and a total of about 2000m2 of usable meeting space. The estimated budget is higher than our original expectation, but the hope is that the building could potentially be delivered in phases. Additional work is going on behind the scenes to complete the other documentation to support he planning application and a pre-application review is to be scheduled with the City Council in May.

At 10:15 on Friday 5th February, we completed the purchase of the former MFI site on Castle Boulevard—the future home for the ministries of Cornerstone Church for generations to come.
It was just under 2 years ago that we first started praying and searching in earnest for a new location for the church to meet. Since that time, we have spent many hours looking at a variety of different locations. The purchase itself took a total of 10 months from the beginning of negotiations in May last year to its final completion on the 5th February 2010.
We give thanks and praise to God for his provision of this land in such a strategic location. We are continuing to bring our hopes, fears, expectations and future plans to God, asking for His wisdom and guidance as we continue along this tremendous journey of faith for our church.


Once again we were able to celebrate God’s faithful provision to us. The November Gift Day raised approximately £76,000, which when combined with the gifts and standing orders that came in throughout the month, the total raised was enough to purchase the Castle Boulevard site without a mortgage.
The December edition of Evangelicals Now featured an article entitled ‘Cornerstone – How a large church grew from small one in Nottingham’. It described the last forty years of Cornerstone’s history in conjunction with the celebration of Peter and Valerie Lewis’s ministry in Nottingham. The article ends with a reference to the building project and Cornerstone once again ‘being on the move’. Click here to read the article in full.
With many encouragements to look back on over the last two years, the church were now looking once again to the future and how the site can be developed to provide a home for the ministries of the church. Design options, financial plans and budget estimates continued to be worked on throughout the month. Keep an eye on the news pages for further updates.

Praise God for answered prayer! On Thursday 29th October, we received formal approval of our application for a change in use of the Castle Boulevard Site and completion of the purchase was set for 5th February 2010.
October saw us pass yet another amazing fund raising milestone. Since January 2009 we have managed to raise a further £1Million! This was yet another tremendous testimony to God’s grace and the generosity of His people. By the end of the month, we had raised just over £2.8million in cash and were about £125,000 short of our target of being able to purchase the Castle Boulevard site debt free.
A week of prayer for the building project was announced for 22nd - 28th November. This would culminate in another gift day. The aim of the gift day was to raise the remaining money to purchase the Castle Boulevard site and start raising funds for its development.
The Building Steering Committee was formed in May 2008 to provide management oversight of the detailed aspects of the project, meeting every two weeks to review progress, discuss issues and make recommendations for how the project is to proceed. This month we were sad to announce that Andrew Thurston would be moving away from Nottingham and would no longer be able to be part of the steering committee. At the same time, we were pleased to be able to announce that Debbie Dickson had accepted the invitation to join the steering committee.

On Wednesday 23rd September, the Elders met for the day to discuss and pray for the building project. A review of the last 3 months of the project took place, including the various changes since the Church Meeting in May.
The way forward for the project was discussed and prayerfully considered. The Elders unanimously affirmed the decision to proceed in faith with the purchase of the Castle Boulevard site, whilst investing further time in investigating options to bring the development budget within our provisional estimates. The key points underpinning this decision were:
Throughout September, discussions took place between the church and Nottingham City Council to agree the terms of the Section 106 obligation associated with our planning application. The agreement needed to include a commitment to promoting alternative modes of transport to the site, which is deemed to be in a city centre location. Discussions were productive and a draft agreement was drawn up for approval by ourselves, the vendor and the City Council.

This month was almost exclusively given over to discussions about the future design of the buildings on Castle Boulevard. Working with our chosen architects and a team of specialist consultants, we investigated the opportunities and constraints that the site presents us with.
As well as discussing the different plans for the layout of the East and West buildings, we also carried out investigations on other specialist areas. These included acoustic requirements, a structural assessment of the two buildings, the environmental characteristics of the site, heating and ventilation considerations and fire safety design.
In addition to these studies, work began on estimating costs for the development work. Once complete, this will enable us to refine our business plan and arrive at a budget for the first phase of the construction project.

Thanks and praise to God! Contracts were finally exchanged on Thursday 2nd July for the former MFI premises on Castle Boulevard. This meant that the Church were now formally committed to purchasing the land and buildings on the site, subject gaining planning permission for a change of use to a place of worship. This very significant milestone in the life of the Church marked the end of nearly two months of contract negotiations and many more months of searching for a suitable location.
On 22nd July, the City Council Development Control Committee discussed our application for a change of use of the former MFI premises on Castle Boulevard to class ‘D1 - Place of Worship’. The Committee gave provisional approval to the application subject to us completing a "Section 106" planning obligation with the City Planning Department.
This month, a group visited Kings Gate Church and Conference Centre in Peterborough. The Centre was featured in a BBC programme for Pentecost entitled, ‘That’s the Spirit’. The church has two services each Sunday morning, with about 800 at each and an auditorium which can hold about 1400 people. We were made very welcome and it was great to discuss ideas as well as their recent hands-on experiences of a large building project.

After a lengthy review process, we selected FeildenCleggBradley Studios (FCBs) as our architects for the initial design phase of the project. FCBs were first established in 1978 and have offices in Bath and London. They came with an excellent reputation within the industry and a diverse portfolio of projects from which to draw experience and ideas. We were originally introduced to them through the Orphan Care Hospice project they undertook with Paul and Ann Dean in Inguavuma.
This month we also received news that the Bluecoat School, in which the Church currently meets, intended to pursue the option of further developing the Aspley Lane Campus rather than redeveloping the Wollaton Park Campus. Their aim was for all students to be moved to a consolidated school at the Aspley Lane Campus by 2012. The implications of this announcement were that we would be able to continue to worship at the Wollaton Park Campus until development of the Castle Boulevard site is complete. It was also confirmed that we would be able to keep the offices at the school until Easter 2010.

At a Special Resolution Meeting on 7th May, the Church members voted by an overwhelming majority (98%) to purchase and create plans for the development of the former MFI buildings on Castle Boulevard. This was a tremendously encouraging result and yet another indication that the Lord has been leading us forward one step at a time.
In addition to the tremendous news of the members’ vote, we were also immensely grateful to God for the news that our third gift day had raised an estimated additional £460,000 for the building fund. By the end of May, we had just over £2.5million in available funds, with a further £1million pledged over the next 2-3 years.
Our application for change of use of the Castle Boulevard site was submitted along with supporting planning and transport statements. These can be viewed on the City Council websiteand was scheduled to be decided by 23rd July.
Programme activity also continued throughout the month, with contractual discussions continuing between ourselves and the vendor. We also carried out a number of buildings due diligence tasks this month including a building condition survey, environmental study and valuation report.

It’s hard to believe that twelve months has passed since the search for a new location and fund raising efforts began in earnest, following the Church Annual General Meeting on 3rdi April 2008. At this year’s AGM - exactly twelve months later - the Church members voted to support the Elders and Steering Committee in pursuing the MFI property with a view to voting at a special meeting in May on purchasing that property. All of this resulted in making April 2009 the busiest month of the programme so far.
A significant development such as this needed to be accompanied by serious prayer and giving. A further week of prayer was held from the 19th - 25th April to place ourselves, our plans, hopes and fears in our Lord’s mighty hands once again. This was followed with another gift day, the third in twelve months, on Sunday 26th April.
This month marked the beginning of discussions on the sale contract. We chose Shoosmiths solicitors to represent us in this critical phase of the project. Heads of terms were agreed and the first draft of the contract issued for our review and comment. As well as the contractual discussions, work began on planning and transport statements to support our application for a change of use of the property from its current classification as ‘A1 - Retail’ to ‘D1 - Place of Worship’.
Finally, members of the congregation were invited to visit the Castle Boulevard site to enable as many as possible to see for themselves the potential that the site offers. Two visits were arranged and a good number of people came to have a look around.

At the end of February, we received telephone calls regarding the availability of the former MFI site on Castle Boulevard (NG7 1FP). This property had been on our ‘watch’ list from late last year but had been excluded due to the high initial asking price. However with the global recession continuing to affect the property market, the asking price had been further reduced. Much of the month was therefore spent in discussions with agents as to what kind of offer would position the Church as a serious contender for the property.
The property has huge potential:
It also presents a number of challenges, which the Church were encouraged to pray about:
This month, we also received proposals from a number of architects to create a generic brief for the project. The goal of the brief will be to:

February was a month of small yet significant developments. For example, the building fund surpassed £2,000,000 in available funds. While there is some way to go in terms of fundraising, it is very encouraging to see the faithful giving of God’s people result in this milestone. Anyone who would like to contribute can read about some of the main options by visiting http://www.cornerstoneuk.org.uk/buildingproject/giving.
Another exciting development was the introduction of a second serious contender in terms of suitable properties. Please pray that discussions will be productive and that it will become clear if this is to the site of Cornerstone’s new centre.
With a couple of potential properties being investigated, February was also the month in which a couple of architects were asked to provide generic proposals for a possible church complex. Increasing funds, properties that are potential sites for Cornerstone’s new home and some preliminary proposals from architects are all exciting developments, which bring the project more into focus for us as a church family. However, we realise there is a long journey ahead with major decisions to be made. We want to encourage everyone with an interest in this project to pray that God’s will be clear to the church and that we will have faith, boldness and unity to step forward when that becomes clear.

Everyone at Cornerstone united for a day of prayer and fasting on Thursday 29 January. At this meeting, Paul Couchman shared that there have been recent discussions with the owner of a property that meets many of our requirements. For reasons of commercial sensitivity, we cannot communicate the details, however, there are a number of hurdles and concerns that need to be addressed before progress can be made. Please pray that it will become clear whether nor this is the site for us; we want God’s will to be done.
The building fund has continued to grow with pledges being honoured and standing orders making a steady contribution. At the same time, it has been very encouraging to receive gifts from people who used to attend Cornerstone but have since moved away, some many years ago. We are very grateful for the generosity of God’s people.
Lastly, the process started to select a professional services company. Proposals have been requested and we will be continuing discussions over the coming weeks. We want to be ready to ‘hit the ground running’ with design and planning activities, etc, when the time comes.


With Christmas on the horizon, December was a month of relatively low activity. With no significant new developments to report, church members were encouraged to continue praying for:
Proposals started to be received from a number of professional services organisations in order to be prepared for any increase in activity, should a suitable location be found.
Paul Couchman confirmed that he will continue to perform the role of project manager, albeit with a reduced time commitment, until next steps in the building programme are clarified and/or a successor is appointed.
Please continue to support us in this exciting project.

The month began with the second Gift Day on 2nd November. The results continue to be very encouraging, with the total building fund, including pledges, now just under £3 million.
Another significant fundraising event this month was the auction held at Trent Vineyard on Saturday 15th November. This was a well attended and fun evening, during which people paid handsomely for a range of highly desirable lots! As a result, almost £10,000 was raised for the building fund. Thank you to everyone who donated item, attended and/or bought something. A small number of items were unsold. These can be viewed at: http://www.cornerstoneuk.org.uk/files/auctionitems1.pdf and if you want to make an offer, please contact the church office.
Lastly, at the end of the month (27th), there was a well attended church members’ meeting. One of the agenda items was a building programme update. Paul Couchman gave an update during which he explained our stronger financial position given the month’s giving and fundraising. He also explained that the search for a site was continuing and that the discussions with one previously discussed confidential site were ongoing.
With an eye to the future, Paul explained that the church was now seeking to appoint a professional services company that would be a ‘one stop shop’ for the Church’s multiple requirements once a site had been chosen. Joff Gribbin, one of the elders, thanked Paul for his excellent work as project manager since our requirement for a new building became apparent earlier in the year. Joff explained that there would be a search for a new project manager in the near future as Paul would soon be moving on to other things and hence unable to perform the project manager role on a full-time basis.
The church meeting ended with a call to continue praying for:
We would encourage you to please join us in this exciting project. We very much need and appreciate your support.

October has been one of the more eventful and active months since the launch of the building programme.
On Monday 13th October, a special meeting was held to provide an update on building programme progress. The first item for discussion was that we have identified a freehold property in an excellent location, which seems to be a great possibility for us. The owner has requested that details of the site be kept confidential at this point until we were in a position to take negotiations to a more advanced stage. However, it is thought that the property is big enough to meet Cornerstone’s current needs with potential for expansion in the future.
The second main topic at the update meeting was fundraising. The site has an existing building that would need to be modified and/or extended and therefore we would need to raise at least £4 million to achieve this. While good progress has been made in terms of donations and pledges, it was evident that there is some way to go in terms of getting enough money to avoid having to borrow heavily.
With a view to boosting funds, two forthcoming events were promoted during the month. Firstly, our second gift day on Sunday 2nd November. Everyone was encouraged to consider and pray about giving more, bringing forward the payment of future pledges or maybe giving for the first time. Secondly, an auction is taking place at the Vineyard Church on Lenton Lane on Saturday the 15th November starting at 7.45pm. A wide range of items were donated during the month, from holidays in the sun to a years’ supply of cake, as members and friends of Cornerstone were encouraged to spread the word.
Look out for next month’s news when we’ll be able to provide an update on the Gift Day, the results of the auction and an important members’ meeting taking place on 27th November.

After a relatively quiet summer for the Building Programme, September saw an increase in activity on a couple of fronts.
The Church Weekend provided an opportunity to bring everyone at Cornerstone up to date with developments. On the Sunday morning we got a comprehensive update on the building programme including an update on the status of the building fund which focused minds on the significant fundraising challenge faced by the church. In the same presentation, information about some of the sites under consideration provided everyone with tangible examples of where our future home may be.
All this equipped the Church for a special week of prayer when we were able to devote significant time to pray for our gospel ministry at home and abroad. We also prayed for all aspects of the building programme, including: continuing to preserve the unity of the Church, a suitable new location, progress with fund raising, sound decision making, temporary arrangements and the programme team.
This month, the Elders held an away day to review the overall progress of the building programme. Their time together included prayer for the project, a review of the financial situation and discussion of a number of potential sites. The results of the away day were set to be communicated to the Church during October.
Lastly, a new building programme website was launched (where you are probably reading this update!). We want to keep everyone with a link to Cornerstone, where in the past or today, up to date with news about our building challenge. Look out for more news in the weeks and months to come!

Summer holidays meant a relatively quiet month in relation to site search activity. However, a significant milestone was surpassed on the fundraising front. During the month of August, the amount of money actually given to the building fund (as opposed to pledges) passed the £1 million mark. This is an important first step towards our overall target of £6million for the project.
This month also provided us with a potential foretaste of things to come with a temporary move (for two Sundays) to the Bluecoat Aspley Lane Campus, while electrical work was carried out on the Wollaton Campus. This presented a significant logistical challenge for Spencer and the team, but went smoothly with the help of an army of volunteers and good planning.

Overall, activity levels dropped a little given the onset of the summer holidays. However, Paul gave an update on Building Programme progress and activity to date at the Members’ Meeting on 10 July. After members of the Steering Committee and other teams were introduced, Paul shared the current financial position which included the significant amount of giving and pledges from last month’s Gift Day. This was encouraging but we still have some way to go.
More detail about our building and site requirements was also communicated at the Members’ Meeting. While specific details of potential sites couldn’t be revealed in case it unhelpfully impacted ongoing discussions, it was clear that the search for a suitable site had been active and that a number of sites have been reviewed and considered. None of these sites met all our requirements. We heard that discussions with the school had re-opened regarding the possibility of Cornerstone in some way sharing the redeveloped site at Wollaton Park.

The month began with our first official Building Fund Gift Day. At both services on 1 June (and 7 June for those who were absent the previous week) everyone was encouraged to return the form, which was distributed last month, detailing the financial contribution they had decided to make to the Building Fund. Giving options included one-off donations and future pledges, whether in the form of a lump sum or regular giving. The total amount given or pledged was £841,690 (including an estimate of £150,000 reclaimable tax). This takes the overall value of the building fund to £1,672,287. We give thanks to God for the sacrificial giving of his people.
There were two major developments in the organisation of the Building Programme. The first was the formation of a Steering Committee. Comprised of Joff Gribbin, Spencer Hampton, Stephen Pinfield, Andrew Thurston and Paul Couchman, the purpose of the committee is to provide management oversight to all aspects of the Building programme. It will be accountable to the Elders, providing them with regular updates on progress as well as recommendations for key decisions to be made.
Secondly, Paul Couchman has defined the structure of the Building programme; that is, all the different teams he believes need to be in place to ensure everything that needs to be done, gets done. So, in addition to the Steering Committee there are teams (some large, some small) focusing on communication, strategy and requirements, fundraising, site acquisition, business planning and transition planning. The formation of these teams has started, utilising the skills and abilities of people throughout Cornerstone who are willing to give of their free time and expertise to help with the Building Programme.

This month we have started to get greater focus on our twin challenge namely: finding a location and raising the funding. We estimate that we will need to raise £6Million to purchase a site and develop a building that will meet our vision for Cornerstone’s ministries for the next 100 years. We estimate £3-4 million will be needed to purchase a suitably large site within our target area (within 1.5 miles of the Queen’s Medical Centre) and up to £2 million required for the building.
A Gift Day has been scheduled for the 1st June and an accompanying giving guide has been published and distributed to every member of the Church. Everyone has been asked to prayerfully consider their response to the challenge of raising the money for a new centre for our Church.
Paul Couchman has been appointed, on a temporary basis, to manage and coordinate all of the activities needed to make sure the Building Programme is successful. His management skills and experience will help ensure a coordinated and organised approach to what will be a complex and long-term project.
Finally, a Frequently Asked Questions booklet was published to help address some of the more common questions and concerns that have been raised to date.

This month, we received the news that the redevelopment of the School site was scheduled to go ahead in January 2010 and that the Church would need to find a new location in which to meet from the end of 2009.
News of our new building challenge was communicated to everyone, including a call for a special and intense period of prayer to focus on the issue of Cornerstone’s future accommodation needs. A week of prayer and a number of Prayer and Praise meetings were devoted exclusively to future building requirements. The focus was on locating, acquiring and financing a suitable site or premises, managing the period between leaving the church and having a new building and, of course, caring for our church family and continuing to grow for God’s glory.

